Installation Procedure
Where to use the Soft Landing System (SLS)
The purpose of the system is to reduce the fall potential of personnel
working at height and, in doing so, eliminate or reduce incidence
of injury.
- SLS has been designed for use principally inside a building
during construction, where the "Soft Bags" are constrained
against lateral movement by walls or partitions. For example,
in residential construction.
- SLS can be used for other applications in conjunction with
a webbing constraint system, designed to maintain functionality
of the system. For example, on top of and surrounding “catch”
platforms and leading edge protection.
Checking Bags
Each bag must be visually inspected to ensure that there is no
damage to the outer casing. The clips must be inspected for damage
to ensure that they are fully operational. Any build up of mortar
or mud should be removed with a stiff hand brush. The overall appearance
of the bag should be assessed to check if the energy absorbent material
has not been crushed.
Installation at Ground Floor
The concrete site should be cleared of all rubbish and sharp objects
and swept out to provide a clear surface on which to install the
bags. Working from one corner, clip the “Soft Bags”
together to form a complete unit. As each bag is installed it must
be pushed hard into the previous bags to ensure that a continuous
mat is assembled. Ensure all clips except those on the perimeter
are used. Where the area of floor to be covered by the final row
of bags is smaller than the length or width of bag, simply allow
the bag to curve up the perimeter wall. (This should direct a falling
body onto the “Soft Landing System”). It is advisable
to protect the perimeter of the SLS from falling mortar by means
of strips of polythene etc.
Checking Installation
Once the bags are installed the “Foot Test” should
be carried out. This is a simple way to check that the bags have
been correctly installed. If the bags have been correctly installed,
you will be unable to push your foot in-between the bags. (See installation
guide). If the foot test fails, additional bags should be installed
or the webbing constraint system modified to ensure effectiveness
of the “Foot Test”.
Installation at First Floor Joists
Once first floor joists are fixed, the “Soft Bags”
can be used for protection on the first floor. (Note: - The “Soft
Bags” weigh under 7Kg and are easily handled by one person,
however extra care should be taken in strong winds) At first floor,
it is recommended that the bags are laid on “Weather Deck”
or similar weatherproof flooring or on temporary boarding. Particular
care should be taken at stairwells which must be adequately boarded
over to ensure that a firm base is in place for the bags. The bags
will not span a stairwell without support. Use scaffold boards or
similar, directly on the joists at right angles to the joists, to
provide an adequate safe working platform for operatives to install
the “Soft Bags”. Once a safe working platform has been
established the installation is the same as at ground floor.
Installation in Multi-Storey Buildings
Dependant on the construction method, installation of the “Soft
Bags” follows the same basic procedures as above and is applicable
where the fall potential is below 2.5 metres. It is essential that
a safe working platform is in place for the operatives passing the
bags from one floor to another. The “Soft Bags” are
extremely strong but like all equipment should be treated with care
to ensure a long life.
Caution
SLS has been tested at a 3.5 metre fall potential (that is, 3 metres
from fall level to top of SLS), with satisfactory results.
However, it is recommended that, wherever possible, the fall potential
be reduced to less than two metres when using SLS. If the fall potential
exceeds 2 metres a further layer (or layers) of “Soft Bag”
will be required.
The SLS bags are very strong but should only be walked on where
absolutely necessary. Continual walking on the bags will eventually
compress the energy-absorbing fill and thus reduce the active life
expectancy of the bags.
Installation Supervision
Competent personnel, trained and certificated by IRM Services
Pty Ltd staff or their appointed agents, should only carry out the
installation of the SLS. Once the installation is complete a designated
person employed by the main contractor/developer should approve
it. Each company will have its own system for signing off the installation;
we have however a sample form that can be used if required, these
are available from our main office.
Reporting System
Where someone has fallen into the Soft Landing System the details
of the fall should be reported to our office. This will allow collection
and analysis of data for use in improving the design of SLS. A sample
reporting form is available from our office.
Safe Work Method Statement
A sample Safe Work Method Statement suitable for residential construction
has been provided. This can be adjusted for other applications as
required. To download this SWMS click below.
|